PROJECT STATUS UPDATE
December 04, 2024
-
- USDA Coordination
- Contract Documents (Contracting Language, Plans, Specifications) have been submitted and approved.
- We are currently working on the permits and ROW map.
- TCEQ Coordination
- Submitted to TCEQ on October 18, 2024
- Anticipate a 60-Day Review
- Surveying
- Scope Remaining:
i. One additional Gas Line Crossing along I-10 ii. Airport Tank Site - at the entrance to the airport building
- at the exit of the airport building
- at the fence line at the building
- before the 45 deg bend along 285.
- After the 45 deg bend along 285
- Schedule:
i. As discussed, let’s plan for Nov. 6th. If anything changes please let me know. - Permitting (Currently being worked on)
- TxDOT
- County
- Railroad
- ROW Map for USDA
- TCEQ Well Exception
- Groundwater District
- Minor Plans Edits before Bidding
i. Add meters that were part of negotiated easements. ii. Sheets 49-50 – Billy will pothole the line along highway 285 to determine pipe(s) diameters and to locate all lines to update plans. iii. Add gas line crossings - Wells, Pump Station, and Ground Storage Tank
i. SCADA Plan Updates and Specifications ii. Billy will pothole at Airport Tanks Site - AMR
i. None - Revised Schedule
- USDA/TCEQ Review of Plans, Specifications, and Contract Documents – 60 days (October 2024 - December 2024)
- Request Closing Instructions from USDA – 60 days (December 2024 – February 2025)
- Advertisement for Bid – 30 days (February – March 2024)
- Bid Reviews, Recommendation for Award, Award of Contracts – 30 days (March – April 2024)
- Execution of Contracts – 30 days (April – May 2024)
- Construction (Likely 3 Contracts: Wells/Pump Station, Storage Tank, Water Line) – 365 days (June 2025 – June 2026)
- USDA Coordination