PROJECT STATUS UPDATE

    1. USDA Coordination
      1. Contract Documents (Contracting Language, Plans, Specifications) have been submitted and approved.
      2. We are currently working on the permits and ROW map.
    2. TCEQ Coordination
      1. Submitted to TCEQ on October 18, 2024
      2. Anticipate a 60-Day Review
    3. Surveying
      1. Scope Remaining:

                                                                  i.      One additional Gas Line Crossing along I-10

                                                                 ii.      Airport Tank Site

          1. at the entrance to the airport building
          2. at the exit of the airport building
          3. at the fence line at the building
          4. before the 45 deg bend along 285.
          5. After the 45 deg bend along 285
      1. Schedule:

                                                                  i.      As discussed, let’s plan for Nov. 6th. If anything changes please let me know.

    1. Permitting (Currently being worked on)
      1. TxDOT
      2. County
      3. Railroad
      4. ROW Map for USDA
      5. TCEQ Well Exception
      6. Groundwater District
    2. Minor Plans Edits before Bidding
      1. Water Line Plans

                                                                  i.      Add meters that were part of negotiated easements.

                                                                 ii.      Sheets 49-50 – Billy will pothole the line along highway 285 to determine pipe(s) diameters and to locate all lines to update plans.

                                                               iii.      Add gas line crossings

      1. Wells, Pump Station, and Ground Storage Tank

                                                                  i.      SCADA Plan Updates and Specifications

                                                                 ii.      Billy will pothole at Airport Tanks Site

      1. AMR

                                                                  i.      None

    1. Revised Schedule
      1. USDA/TCEQ Review of Plans, Specifications, and Contract Documents – 60 days (October 2024 - December 2024)
      2. Request Closing Instructions from USDA – 60 days (December 2024 – February 2025)
      3. Advertisement for Bid – 30 days (February – March 2024)
      4. Bid Reviews, Recommendation for Award, Award of Contracts – 30 days (March – April 2024)
      5. Execution of Contracts – 30 days (April – May 2024)
      6. Construction (Likely 3 Contracts: Wells/Pump Station, Storage Tank, Water Line) – 365 days (June 2025 – June 2026)