UPDATED PROJECTED TIMELINE
July 21, 2023
- Attorney Easement Review/Title Opinion – 60 to 90 days (August/September 2023)
- Develop Plans, Specifications, and Contract Documents (concurrent with #1) – 90 to 120 days (September/October 2023)
- USDA/TCEQ Review of Plans, Specifications, and Contract Documents – 60 to 90 days (November 2023 - January 2024)
- Request Closing Instructions from USDA – 60 days (January - March 2024)
- Advertisement for Bid – 30 days (February – April 2024)
- Bid Reviews, Recommendation for Award, Award of Contracts – 30 days (March – May 2024)
- Execution of Contracts – 30 days (April – June 2024)
- Construction (Likely 3 Contracts: Wells/Pump Station, Storage Tank, Water Line) – 365 days (April – June 2025)