Welcome to the Official Website of Pecos County Water Control Improvement District No. 1

Our Mission

At Pecos County Water Control Improvement District No. 1, we are committed to providing safe, high quality water services to our community, while maintaining a standard of excellence in customer service and environmental conservation.

Bill Payment Options

Looking for the most convenient way to pay your bill? We offer a wide variety of payment options to our customers. Simply choose the option that best suits your needs...Payment Options...

Conservation Tips

There are a number of easy ways to save water, and they all start with you. When you save water, you save money on your utility bills. Here are just a few ways...Conservation Tips

Recent News View All »

UPDATED PROJECTED TIMELINE

July 21, 2023

  1. Attorney Easement Review/Title Opinion – 60 to 90 days (August/September 2023)
  2. Develop Plans, Specifications, and Contract Documents (concurrent with #1) – 90 to 120 days (September/October 2023)
  3. USDA/TCEQ Review of Plans, Specifications, and Contract Documents – 60 to 90 days (November 2023 - January 2024)
  4. Request Closing Instructions from USDA – 60 days (January - March 2024)
  5. Advertisement for Bid – 30 days (February – April 2024)
  6. Bid Reviews, Recommendation for Award, Award of Contracts – 30 days (March – May 2024)
  7. Execution of Contracts – 30 days (April – June 2024)
  8. Construction (Likely 3 Contracts: Wells/Pump Station, Storage Tank, Water Line) – 365 days (April – June...